Permits & Regulations••Last verified Sep 1, 2026
Your Permit Was Approved — What Happens Next?
Getting your permit is not the finish line. Mandatory inspections take place at critical stages of construction.

Once a building permit is issued, the work must be built according to the approved plans and the Ontario Building Code.
MANDATORY INSPECTIONS
Toronto Building inspects work at critical stages of construction — for example footings and foundations, framing, plumbing, insulation and fire separations, and the final inspection. The required inspections depend on the project and are listed with your permit.
YOUR RESPONSIBILITIES
• The builder or owner must request each required inspection — the City does not schedule them automatically.
• Do not cover work (for example with drywall or backfill) before its required inspection is completed.
• Keep the permit and approved drawings available on site during construction.
• Correct any deficiencies an inspector identifies and request a re-inspection if needed.
• Book the final inspection when the work is complete so the permit can be closed.
WHY IT MATTERS
An open permit, or work covered before inspection, can delay a sale or refinancing and may require work to be opened up later.
Source
City of Toronto — Building Inspections
ConstruWeb provides a plain-language summary. The official source is the authority — always confirm details there.